Day works docket

Day works docket is one of Demiton's published registers for Australian civil construction. Day works dockets for extra or variation work. Demiton keeps it current from the systems a contractor already runs and publishes the record's shape as a versioned JSON Schema, so the same question works whichever system produced the record.

Part of Contracts in the register catalog.

Register ID
day_works_docketUse this name to ask for the register. The API calls it a shelf ID.
Each record is
An eventSomething that happened at a point in time.
Status
AvailableFilled today from connected systems, uploads or public data.
Data
OrganisationPrivate to each organisation's own workspace.
Version
v2 (2.0.3)Current version.

Standards

This register's contract was designed against these standards and laws. Holding these records does not by itself certify compliance.

  • AS 4000General Conditions of Contract (superseded edition, still in use)Australia · 1997 · clause cl 37.1/37.2 (per commentary) · paywalled, from a secondary description
  • AS 4000General Conditions of Contract (construct only)Australia · 2025 · clause cl 20 (per commentary) · paywalled, from a secondary description
  • AS 4902General Conditions of Contract for Design and ConstructAustralia · 2000 · paywalled, from a secondary description
  • Security of paymentAustralian state and territory Security of Payment Acts (NSW 1999, QLD 2017, VIC 2002, WA 2021, SA 2009, TAS 2009, ACT 2009, NT 2004)Australia · various · public summary
  • Privacy Act 1988Privacy Act 1988 (Cth)Australia · current · public summary
  • Security of paymentBuilding and Construction Industry Security of Payment Act 2009 (Tas)Australia · 2009 (in force 2025-10-11) · clause s 17(6) · verified against full text
  • GDPRGeneral Data Protection RegulationEuropean Union · 2016 · verified against full text
  • NZ CCA 2002Construction Contracts Act 2002 (NZ), 2002 No 46, as amended 2015 and 2023New Zealand · as at 5 Oct 2023 · clause ss 17-21 · verified against full text
  • Privacy Act 2020 (NZ)Privacy Act 2020 (NZ)New Zealand · current · public summary
  • HGCRA 1996 Part IIHousing Grants, Construction and Regeneration Act 1996, Part II (as amended by LDEDCA 2009)United Kingdom · 1996 c. 53 as amended · clause ss 110A, 111 · verified against full text
  • SI 1998/649Scheme for Construction Contracts (England and Wales) Regulations 1998United Kingdom · 1998 as amended 2011 · verified against full text
  • UK GDPRUK GDPR and Data Protection Act 2018United Kingdom · as retained and amended · public summary
  • AIA G702/G703Application and Certificate for Payment; Continuation SheetUnited States · 1992 (current base editions) · public summary

Connectors

Connected today

Demiton keeps this register current from these systems now.

On the roadmap

Systems in the planned connector rollout that can fill this register. Partial means the system holds only some of its fields.

  • SitematePartial

Fields

25 fields: 5 required, 20 optional.

Required

Every record carries these fields.

projectNumber

The project or job the extra work was done on.

Example: 8101

work_dateDateYYYY-MM-DD

The calendar day the dayworks were performed, falling back to the diary date.

Example: 2026-07-14

descriptionText

The works performed.

Example: Additional kerb and channel removal due to unforeseen uti…

external_idText

The source row's own identifier.

Example: DWD-2026-0031

occurred_atDate and timeISO 8601, with time zone

When the docket was submitted.

Example: 2026-07-14T16:30:00Z

Optional

Present when the source system records them.

rateTextUnit: currency per hour/unit

The agreed dayworks rate.

Example: 62.00

assetText

The plant or equipment used.

Example: 9302

hoursDecimal numberUnit: hours

Hours of extra work.

Example: 8.5

amountDecimal numberUnit: currency

The docket total.

Example: 4820

workerNumber

The worker the docket is attributed to.

Example: 5503

currencycurrency

The currency of rate/amount

Example: AUD

narrativeGroup of fields

The source form responses.

signatureText

The client sign-off on the docket.

Example: T. Aldous

tax_basisText

Whether rate/amount include GST/VAT.

Example: GST exclusive

delay_daysDecimal numberUnit: days

Estimated delay, in days, attributable to the extra work.

Example: 0.5

attachmentsText

Photo evidence attached to the docket.

creator_nameText

Who filled the docket in.

Example: Aaron Patel

project_numberText

The human project number quoted on the docket.

source_form_idNumber

The id of the form template that produced the row.

Example: 4410

client_referenceText

The client's own docket or PO reference.

Example: CHRC-DW-014

financial_periodText

The period the work is attributed to.

Example: 2026-07

source_form_titleText

The title of the form template that produced the row.

Example: Day Works Docket

claimable_under_sopTrue or false

Whether the amount may be included in a Security-of-Payment claim in the governing jurisdiction.

Example: true

client_representativeText

The client's authorised representative.

Example: T. Aldous

contractor_representativeText

The contractor's authorised representative.

Example: Aaron Patel

Filed against

Records are indexed along these dimensions, so they can be asked for by any of them.

  • Financial periodcontext for the record, from When known
  • Workerwhat the record is about, from When known
  • Projectwhat the record is about, from Always set
  • Assetwhat the record is about, from When known

Example record

A sample from Bridgeworks Group, Demiton's demonstration company. The values are illustrative; the shape is exactly what the contract describes.

day_works_docket.example.json
{
"amount": 4820,
"asset": "9302",
"claimable_under_sop": true,
"client_reference": "CHRC-DW-014",
"client_representative": "T. Aldous",
"contractor_representative": "Aaron Patel",
"creator_name": "Aaron Patel",
"currency": "AUD",
"delay_days": 0.5,
"description": "Additional kerb and channel removal due to unforeseen utility conflict",
"external_id": "DWD-2026-0031",
"financial_period": "2026-07",
"hours": 8.5,
"narrative": {
"work_performed": "Excavated and relocated unmarked stormwater line"
},
"occurred_at": "2026-07-14T16:30:00Z",
"project": 8101,
"rate": "62.00",
"signature": "T. Aldous",
"source_form_id": 4410,
"source_form_title": "Day Works Docket",
"source_system": "ASSIGNAR",
"tax_basis": "GST exclusive",
"work_date": "2026-07-14",
"worker": 5503
}

Version history

  • v2 (current)
  • v1

Use this contract

The contract is a standard JSON Schema (draft 2020-12) document, so any JSON Schema validator can check a record against it. Keywords starting with x-demiton- add Demiton's own meaning, such as units and requiredness, and validators ignore them.

Schema URL
https://docs.demiton.io/registers/day_works_docket/v2.json
Show the full JSON Schema

Loading the schema…

Talk to the team

Tell us what you run - your ERP, field, payroll and document systems - and we will show you the registers Demiton would fill from them, on your data, in a 30-minute call.

Book a 30-minute callStart free