Skip to content
Demiton

Plant prestart (v1)

Plant prestart is one of Demiton's published registers for Australian civil construction. Daily plant and equipment pre-start checks: condition, defects, compliance. Demiton keeps it current from the systems a contractor already runs and publishes the record's shape as a versioned JSON Schema, so the same question works whichever system produced the record.

Part of Safety in the register catalog.

Register ID
plant_prestartUse this name to ask for the register. The API calls it a shelf ID.
Each record is
An eventSomething that happened at a point in time.
Status
AvailableFilled today from connected systems, uploads or public data.
Data
OrganisationPrivate to each organisation's own workspace.
Version
v1 (1.0.1)Superseded by v2.

Standards

This register's contract was designed against these standards and laws. Holding these records does not by itself certify compliance.

  • AS 2550Cranes, hoists and winches - Safe use - Mobile elevating work platformsAustralia · 2025 · paywalled, from a secondary description
  • AS 2550Cranes, hoists and winches - Mobile elevating work platforms (design and construction)Australia · 2025 · paywalled, from a secondary description
  • WHS Act and RegulationsModel Work Health and Safety Regulations (Safe Work Australia; given effect by each state/territory)Australia · as amended 5 December 2025 · clause regs 81, 226, 234, 235(4), 237; Sch 3, 5 · verified against full text
  • ISO 45001Occupational health and safety management systems - Requirements with guidance for useInternational · 2018 + Amd 1:2024 (AS/NZS ISO 45001:2018 AU/NZ adoption) · clause 8.1 · paywalled, from a secondary description
  • ISO 55001Asset management - Vocabulary, overview and principlesInternational · 2024 (AS ISO 55000:2024 identical AU adoption) · paywalled, from a secondary description
  • ISO 55001Asset management - Asset management system - RequirementsInternational · 2024 (AS ISO 55001:2024 identical AU adoption) · clause 8.1; 7.6 · paywalled, from a secondary description
  • ISO/TS 15143-3Earth-moving machinery and mobile road construction machinery - Worksite data exchange - Telematics data (AEMP 2.0)International · 2020 (SA TS ISO 15143.3:2021 AU and PD ISO/TS 15143-3:2020 UK identical adoptions) · paywalled, from a secondary description
  • LOLER 1998Lifting Operations and Lifting Equipment Regulations 1998United Kingdom · 1998 (with HSE ACOP) · clause Schedule 1 · public summary
  • OSHAOSHA - Overhead and gantry cranesUnited States · eCFR current (read 2026-09-01 point in time) · clause (j) · verified against full text

Connectors

Connected today

Demiton keeps this register current from these systems now.

On the roadmap

Systems in the planned connector rollout that can fill this register. Partial means the system holds only some of its fields.

  • EROAD
  • GeotabPartial
  • HammerTech
  • MittiPartial
  • Sitemate

Fields

20 fields: 5 required, 13 optional, 2 defined by each organisation.

Required

Every record carries these fields.

assetNumber

The item of plant the prestart is about.

Example: 9301

external_idText

The source form-result's own identifier, as text.

Example: PP-2026-8891

occurred_atDate and timeISO 8601, with time zone

When the prestart was submitted; the date the retention clock runs from.

Example: 2026-07-14T21:30:00Z

flagged_countWhole number

How many answers name a fault; the shelf's primary condition signal.

Example: 0

source_systemText

Which bound system emitted the row; ASSIGNAR today.

Example: ASSIGNAR

Optional

Present when the source system records them.

workerNumber

The worker who submitted the prestart; an anchor, not a declared axis.

Example: 5501

form_idNumber

The source form template identity.

Example: 211

projectNumber

The project the plant was pre-started on that day.

Example: 8101

certifierText

The competent person who performed or certified the prestart.

Example: Aaron Patel

jurisdictionText

The WHS/examination regime whose interval and retention rule apply.

Example: AU-QLD-WHS

source_unitsGroup of fields

The source unit each measure arrived in, beside the canonical unit.

tag_severityWhole number

The green/yellow/red plant tag at its worst on the form.

Example: 1

prestart_dateDateYYYY-MM-DD

The date the form itself carries, where it differs from submission time.

Example: 2026-07-14

narrative_countWhole number

How many free-text answers were filled in.

Example: 2

inspection_classText

Pre-operational / routine / major inspection.

Example: pre-operational

unanswered_countWhole number

How many answerable questions were left blank.

Example: 0

hour_meter_readingDecimal numberUnit: hours (unit unverified)

The machine's hour-meter reading recorded at the prestart.

Example: 4123.5

asset_registration_numberText

The registration number for plant that must be registered before use.

Example: QLD-PLT-88210

Defined by each organisation

Their contents come from the organisation's own forms or systems, so they differ between organisations.

form_titleText

The tenant's own name for the prestart form the record was captured on; the key the form_pattern sweep matches.

Example: Plant Prestart Checklist

tenant_payloadGroup of fields

The tenant's own prestart questions and answers — check-item results, selectors, comments, the grout/mixer numerics.

Example record

A sample from Bridgeworks Group, Demiton's demonstration company. The values are illustrative; the shape is exactly what the contract describes.

plant_prestart.example.json
{
"asset": 9301,
"asset_registration_number": "QLD-PLT-88210",
"certifier": "Aaron Patel",
"external_id": "PP-2026-8891",
"flagged_count": 0,
"form_id": 211,
"form_title": "Plant Prestart Checklist",
"hour_meter_reading": 4123.5,
"inspection_class": "pre-operational",
"jurisdiction": "AU-QLD-WHS",
"narrative_count": 2,
"occurred_at": "2026-07-14T21:30:00Z",
"prestart_date": "2026-07-14",
"project": 8101,
"source_system": "ASSIGNAR",
"tag_severity": 1,
"unanswered_count": 0,
"worker": 5501
}

Version history

  • v2 (current)
  • v1

Use this contract

The contract is a standard JSON Schema (draft 2020-12) document, so any JSON Schema validator can check a record against it. Keywords starting with x-demiton- add Demiton's own meaning, such as units and requiredness, and validators ignore them.

Schema URL
https://docs.demiton.io/registers/plant_prestart/v1.json
Show the full JSON Schema

Loading the schema…

Talk to the team

Tell us what you run - your ERP, field, payroll and document systems - and we will show you the registers Demiton would fill from them, on your data, in a 30-minute call.

Book a 30-minute callStart free